Facade insulation and finishing in crepi - Asse
Insulating and protecting a semi-detached house
images
Photos
CLEYS
Project details
Start of works
May 2024
Execution time
4 weeks
Project type
Facade insulation + crepi finish
Grain & color
1,5 mm - 34P2
Extras
Plinth in granulate grain
Window sills in aluminium
Rainwater pipe in zinc
Surface in m²
145
Location
Asse
Architect
n/a
CLEYS
The challenge
First visit in March 2024 and execution 2.5 months later. A very quick turnaround was crucial here.