Gevelisolatie & Crepi - Kapellen
Voor -en achtergevel geïsoleerd en bepleisterd bij totaalrenovatie
images
Photos
CLEYS
Project details
Architect
n/a
Start of works
January 2024
Execution period
4 weeks
Project type
Facade insulation + crepi
Grain & Color
1mm - 78P0
Extras
Black granular plinth at the front facade
Surface in m²
150
Client
Mr. De Cuyper
Location
St. Niklaas
CLEYS
The challenge
The cold and wet weather during this period was the main challenge. It caused a longer execution period.